How to build a renovation contingency budget
Keep planned costs, actual spending and contingency separate so the project stays understandable.
// HOW TO CALCULATE
Step by step.
- List project categories and obtain written quotes or supplier prices.
- Record planned costs for each category and total them.
- Add a separately identified contingency reserve based on the project’s uncertainty.
- Track actual spending and compare it with planned amounts, including the reserve.
// WORKED EXAMPLE
The numbers.
EXAMPLE
For a $4,850 planned budget and a 10% reserve, the contingency is $485 and the planning ceiling is $5,335. If actual costs reach $4,000, $1,335 remains including reserve.
Sources and further reading
These are explanatory examples, not engineering advice, live price quotes, or guarantees of product yield. Consult manufacturer instructions, local codes and qualified professionals where necessary.