// CONCRETE · METHOD & WORKED EXAMPLE
How much concrete for a slab?
Turn slab length, width and thickness into cubic yards, then into bags or a ready-mix order.
THE FORMULA
Cubic feet = L × W × (thickness in ÷ 12) · Cubic yards = cu ft ÷ 27
// HOW TO CALCULATE
Step by step.
- Measure the slab length and width in feet, and decide the thickness in inches (often 4 in for patios and walks).
- Multiply length × width × thickness ÷ 12 to get cubic feet.
- Add 5–10% for uneven ground and spillage.
- Divide cubic feet by 27 for cubic yards, or by the bag yield for bags (an 80 lb bag makes about 0.60 cu ft).
// WORKED EXAMPLE
The numbers.
EXAMPLE
A 12 × 10 ft patio at 4 in is 12 × 10 × 0.333 = 40 cu ft. With 10% extra that is 44 cu ft, or 1.63 cubic yards. In 80 lb bags: 44 ÷ 0.6 = 74 bags, about $518 at $7 a bag.
// TIPS
Before you buy.
- Above roughly 1 cubic yard, ready-mix delivery is usually easier than mixing bags; most trucks carry about 9–11 cubic yards.
- Compact the base and set forms level before ordering, so the thickness you calculated is the thickness you pour.
- Order a little extra: running short leaves a weak cold joint.
Sources and further reading
- Concrete Network — Concrete calculator and bag counts ↗
- Fine Homebuilding — Tips for specifying, pouring and finishing concrete ↗
These are explanatory examples, not engineering advice, live price quotes, or guarantees of product yield. Consult manufacturer instructions, local codes and qualified professionals where necessary.